Update 4 May 2021

The Gumeracha Main Street Upgrade project will deliver a range of improvements, including underground power lines, a new stormwater system, better pedestrian connectivity and a safer streetscape environment for Gumeracha’s ‘Village Heart’. This community streetscape project is delivered in close partnership with SA Power Networks, the Gumeracha Main Street Group and the Gumeracha Community Association.

The first part of the project, undergrounding of power lines is being delivered by SA Power Networks.

Latest News

Works for the undergrounding of the power lines are in their last stages. SAPN’s contractor have completed all low voltage property connections as well as all cabling works. The energising of cables and the feed-in switch over are scheduled to be completed by mid-June. You might have noticed that the new light columns are currently stored at the Gumeracha oval.

Contractors will be in touch with every household and trader to work out the best time for the switch over from overhead to underground power connections. By end of June all undergrounding works should be complete and overhead cables and stobie pole are supposed to come down from mid-June on!

Due to the delay in the undergrounding works, the stormwater works along Albert Street are now planned for a start in July 2021.

The streetscape upgrade works were tendered successfully and Adelaide Hills Council engaged PLOT Works to deliver this exciting part of the Gumeracha facelift project. Construction of the footpath, kerb and landscaping works is to commence August / September.

Next Steps

  • Complete undergrounding works for the power lines.
  • Remove overhead cables and stobie pole by end of June.

Indicative Timetable

Action / Activity

Indicative Timeline

Undergrounding Power Lines (PLEC)


  • Finalise design / tender for construction

COMPLETE

  • Civil works (trenching)

COMPLETE

  • Cabling

COMPLETE

  • Removing stobie poles

June 2021



Stormwater Upgrade


  • Finalise design / tender for construction

COMPLETE

  • Construction

July - August 2021



Streetscape Improvements


  • Art Wall preparation and installation

COMPLETE

  • Tender for construction

COMPLETE

  • Construction

August/September 21 – January 22


Frequently Asked Questions (FAQ) are available on the right of the main page.

For more information or to join the project mailing list call 8408 0400 or email engage@ahc.sa.gov.au.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>