Update 25 June - Things are really about to start!

Things are really about to start – finally! SAPN are commencing works next week, art installation to start the following week and a new footpath is getting built at the moment to better connect the Big Rocking Horse with the rest of the town.

Trench works for the undergrounding of power lines along Albert Street will naturally have an impact on residents’ and businesses’ access to their properties as well as on parking along the road. SAPN’s contractor David Schwarz will ensure that traffic and pedestrian management during construction will keep all road and footpath users safe while minimising disruptions where possible.

To achieve the best for Gumeracha, this big project will require the help and patience from the whole community.

  • SA Power Network’s contractor David Schwarz will commence works on undergrounding of the power lines from Monday 29 June on.
    Any affected properties and businesses will be consulted with a few days ahead of works impacting on their access.
  • Art installation – Artist Paul Herzich is aiming to commence the art installation of an aboriginal art piece along the entire length of the wall from Monday 6 July on. Works should be complete within approx. 5 days.

Next Steps

  • Council to tender stormwater upgrade for construction.
  • Council to prepare streetscape detailed design for tender for construction.

Indicative Timetable

Action / Activity

Indicative Timeline

Undergrounding Power Lines (PLEC)


  • Finalise design / tender for construction

COMPLETE

  • Civil works (trenching)

29 June – December 2020

  • Cabling

August – December 2020

  • Removing stobie poles

Late 2020 / early 2021



Stormwater Upgrade


  • Finalise design / tender for construction

January – May 2020

  • Construction

Follow PLEC Stage 1,

Commence later this year



Streetscape Improvements


  • Art Wall preparation and installation

6-10 July 2020

  • Finalise design / tender for construction

April – July 2020

  • Construction

Once PLEC Stage 1 is complete

Aiming for Nov/ Dec start


Frequently Asked Questions (FAQ) are available on the right of the main page.

For more information or to join the project mailing list call 8408 0400 or email engage@ahc.sa.gov.au

Photo Credit: Gumeracha Mainstreet Association

Share Update 25 June - Things are really about to start! on Facebook Share Update 25 June - Things are really about to start! on Twitter Share Update 25 June - Things are really about to start! on Linkedin Email Update 25 June - Things are really about to start! link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>