July 2024

Project Staging Area and Project Site Office Burfords Hill Road

The Council reserve off Burford Hill Road has been prepared for use as a project site staging area.  The site office will be located here, and the contractor will underate processing or vegetation.  The reserve has been cleared of dead wood from the Cudlee Creek fires and will be used as a parking area for user of the Amy Gillett.

15 July 2024

Tree Clearance Contractors

Contractors will be establishing on site to commence works at either end of the Amy Gillett corridor.  These contractors will be removing vegetation to allow construction of the path to occur.  The contractor will also be removing dead vegetation or un-stable tress that may pose a risk to construction working and the ultimate users of the shared path.

06 August 2024

Bridge Tender out to Market

Council has tendered out for the construction of the two new bridges required over Angas Creek and William Creek

19 August 2024

Civil Construction Works Commence on Stage 1

Council has commenced construction works on the first 500m path extension from Oval Road, Mount Torrens.  These works will complete our first milestone requirement with our Federal Government funding partner and is tied to the payment of milestone 1 payment.